In Process [In Process]
15% complete, updated on Tue 6/7/22 8:30 AM by Zachary Pahl
Changed Percent Complete from 10% to 15%. Majority of equipment has been ordered. Construction is proceeding more or less as expected.Deliveries are significantly later than expected. Will be relaying/discussing possible timeline changes to stakeholder groups based on this most recent news.
Falcon Promise proposal being put forth by Communications & Media Studies Department to renovate the current NH 315 & associated sub-spaces into two classroom spaces and a conference room.