FacMgmt: NH 315 Renovation (Falcon Promise 2021)

15 %

Status

Project is 15 % complete, starting on Wed 11/18/20 and ending on Fri 9/2/22.

In Process [In Process]

15% complete, updated on Tue 6/7/22 8:30 AM by Zachary Pahl

Changed Percent Complete from 10% to 15%.
Majority of equipment has been ordered. Construction is proceeding more or less as expected.

Deliveries are significantly later than expected. Will be relaying/discussing possible timeline changes to stakeholder groups based on this most recent news.

Details

Dates
Wed 11/18/20 - Fri 9/2/22
Acct/Dept
Facilities Management
Service
Instructional Space / Classroom Technology: Consultation
Type
Projects and Changes / Construction
Health
Green - On track
Classification
Project
Created
Wed 11/18/20 3:32 PM
Modified
Tue 6/7/22 8:30 AM

Description

Falcon Promise proposal being put forth by Communications & Media Studies Department to renovate the current NH 315 & associated sub-spaces into two classroom spaces and a conference room.

Manager

Alternate Manager(s)

Sponsor

Stakeholders (1)

MM
Michael Mueller
Responsible, Accountable, Consulted, Informed
UWRF Facilities Director & Project Initiator
Wed 11/18/20 3:37 PM